Account 241 – Construction in progress
Extract from Appendix II – Circular 99/2025/TT-BTC dated 27 October 2025 of the Ministry of Finance, applicable to financial years beginning on or after 1 January 2026.
Category: Asset accounts
Sub-accounts:
| Code | Level | Account name |
|---|---|---|
| 2411 | 2 | Purchase of fixed assets |
| 2412 | 2 | Capital construction |
| 2413 | 2 | Periodic repair and maintenance of fixed assets |
| 2414 | 2 | Upgrading and renovation of fixed assets |
See also: Accounting principles for fixed assets, investment property and construction in progress
1. Accounting principles
a) This account is used only by entities that have not established a project management board, to reflect the costs of implementing capital construction investment projects (including the purchase of new fixed assets; capital construction of new fixed assets; periodic repair and maintenance; and upgrading and renovation of fixed assets to increase their capacity or extend their useful lives and increase their economic benefits) and the final settlement of capital construction investment costs in enterprises.
Capital construction investment and the periodic repair and maintenance or upgrading and renovation of fixed assets of an enterprise may be carried out by contractors or by the enterprise itself. In enterprises that carry out capital construction investment themselves, this account also reflects costs incurred in the course of construction, installation and repair.
b) The costs of implementing capital construction investment projects are all costs necessary for the new construction or the repair, upgrading, renovation, expansion or technical re-equipment of works. The content of capital construction investment costs is determined in accordance with the current law on the management of construction investment costs. Only costs directly attributable to capital construction investment in fixed assets and investment property (being costs that are necessary and unavoidable in carrying out capital construction investment), where the construction of the assets in progress is not abnormally interrupted due to delays in implementation or delays compared with the expected construction schedule, etc., may be capitalised into the value of fixed assets and investment property.
Borrowing costs directly related to a loan (other than interest payable), such as appraisal, audit and loan application costs, loan arrangement costs, etc., are recognised in financial expenses, except where these borrowing costs arise from a loan specifically for the purpose of investing in, constructing or producing assets in progress and meet the conditions set out in Vietnamese Accounting Standard (VAS) No. 16 – Borrowing costs, in which case they are capitalised. Where the loan is used to invest in subsidiaries, joint ventures, associates, etc., the borrowing costs are not capitalised.
Account 241 is broken down in detail by each work and work item. For each work item, each type of capital construction investment cost must be recorded in detail and monitored cumulatively from commencement until the work or work item is completed, in the condition necessary for it to be capable of operating in the manner intended by the enterprise, and accepted.
Where the enterprise is unable to continue a work or work item that it is constructing, or constructing under a business cooperation arrangement, the enterprise must assess, based on the actual circumstances, the recoverability of the capital construction investment costs incurred; any difference is recognised in the enterprise’s production and business results for the period.
c) In capital construction investment, construction and installation costs and equipment costs are usually charged directly to each work or work item; project management costs and other costs are usually incurred in common. The enterprise must calculate and allocate project management costs and other costs to each work or work item according to the following principles:
- If project management costs and other costs directly related to each work or work item can be identified separately, they are charged directly to that work or work item;
- Project management costs and other common costs relating to several works or work items that cannot be charged directly to each work or work item are allocated on the bases most appropriate to each work or work item.
d) Where a project has been completed and brought to the condition necessary for it to be capable of operating in the manner intended by the enterprise but the final settlement of the project has not yet been approved, the enterprise records an increase in the historical cost of fixed assets at a provisional value (the provisional value must be based on the costs actually incurred and the estimated costs that will certainly be incurred to obtain the fixed asset) for the purpose of depreciation, but must subsequently adjust it to the approved final settlement value.
dd) Costs of regular repair and maintenance of fixed assets in normal operation are charged directly to production and business costs of the period of the department using the fixed assets. For fixed assets that, due to technical requirements, must undergo periodic repair and maintenance, the enterprise may accrue repair and maintenance costs in advance (if it has an obligation) or record the repair and maintenance costs incurred in deferred costs and periodically allocate them to production and business costs of the department using the fixed assets. Costs incurred after initial recognition in connection with upgrading and renovation that increase the capacity or extend the useful life of fixed assets are recorded as an increase in the historical cost of the fixed assets.
e) Enterprises constructing real estate use this account to accumulate the costs of constructing fixed assets or investment property. Where the real estate under construction is used for multiple purposes (as offices, for lease or for sale, for example a mixed-use building), the enterprise still accumulates the costs directly attributable to the construction investment in Account 241 – Construction in progress. When the work or project is completed and handed over for use, the enterprise transfers the construction investment costs according to the nature of each type of asset, based on how the asset is actually used.
g) During the construction investment phase to create fixed assets or investment property, the enterprise must not capitalise exchange differences into the value of assets in progress.
h) Where an investment project is cancelled or suffers losses, the enterprise must liquidate it and recover the costs incurred on the project. The difference between the investment costs actually incurred and the proceeds from the liquidation is recognised in other expenses or as compensation to be recovered from responsible organisations or individuals.
i) For perennial plants yielding periodic produce that qualify as fixed assets (tea, coffee, rubber, pepper, fruit trees, etc.), the costs of land reclamation, land preparation, planting, tending, etc. during the capital construction phase (before maturity, when the plants start to yield their first produce) are reflected in Account 241 – Construction in progress. When the perennial plants yielding periodic produce reach maturity and begin to yield produce, the enterprise transfers the costs from Account 241 – Construction in progress to Account 211 – Tangible fixed assets.
Account 241 – Construction in progress has 4 level-2 accounts:
- Account 2411 – Purchase of fixed assets: Reflects the costs of purchasing fixed assets and the final settlement of such costs where the fixed assets require installation and trial running before being put into use (including the purchase of new or used fixed assets). If purchased fixed assets require further investment or equipment before they can be used, all purchase and additional equipment costs are also reflected in this account.
- Account 2412 – Capital construction: Reflects capital construction investment costs and the final settlement of capital construction investment. This account is broken down in detail by each work and work item (by each asset created through the investment) and, for each asset, each type of capital construction investment cost must be monitored in detail.
- Account 2413 – Periodic repair and maintenance of fixed assets: Reflects the costs of periodic repair and maintenance of fixed assets and the final settlement of such costs. Regular repairs of fixed assets are not recorded in this account but are charged immediately to production and business costs of the period.
- Account 2414 – Upgrading and renovation of fixed assets: Reflects the costs of upgrading and renovating fixed assets and the final settlement of such costs.
2. Structure and content of Account 241 – Construction in progress
Debit side:
- Costs of purchasing fixed assets and investment property (where a construction investment phase or installation and trial running is required);
- Capital construction investment costs of fixed assets or investment property;
- Costs of upgrading and renovating fixed assets;
- Costs of periodic repair and maintenance of fixed assets.
Credit side:
- Value of fixed assets or investment property created through purchase or capital construction investment that have been completed and brought to the condition necessary for them to be capable of operating in the manner intended by the enterprise;
- Value of completed upgrading and renovation works on fixed assets or investment property, transferred when the final settlement is approved;
- Final settlement of periodic repair and maintenance costs of fixed assets when the fixed assets are completed and handed over for use;
- Value of works discarded and other costs approved for write-off, transferred when the final settlement is approved;
Debit balance:
- Costs of purchase, construction investment, periodic repair and maintenance, and upgrading and renovation of fixed assets in progress at the end of the accounting period;
- Value of construction investment in investment property still in progress at the end of the accounting period;
- Value of construction works and periodic repair and maintenance and upgrading and renovation of fixed assets completed but not yet handed over for use, or whose final settlement has not yet been approved, at the end of the accounting period.
3. Accounting method for certain main economic transactions
3.1. Accounting for the purchase of fixed assets requiring installation and trial running
a) Where trial running costs are incurred without producing any output, based on the accounting documents relating to the purchase of the fixed asset, record:
Dr Account 241 – Construction in progress
Dr Account 133 – Deductible VAT (if any)
Cr Accounts 111, 112, etc.
- When trial production costs are incurred, the enterprise accumulates them in Account 241 to calculate the historical cost of the fixed asset, based on the relevant accounting documents, recording:
Dr Account 241 – Construction in progress
Dr Account 133 – Deductible VAT (if any)
Cr Accounts 111, 112, etc.
b) Where trial running produces output or scrap:
- When trial running costs are incurred that generate trial output, the enterprise accumulates all trial running costs in work in progress to calculate the cost of the trial output, recording:
Dr Account 154 – Work in progress
Dr Account 133 – Deductible VAT (if any)
Cr Accounts 111, 112, 152, 331, etc.
- When the trial output is received into the warehouse, record:
Dr Account 155 – Products
Cr Account 154 – Work in progress.
- When the trial output is sold:
- Reflect the revenue from selling the trial output:
Dr Accounts 111, 112, etc.
Cr Accounts 154, 155
Cr Account 3331 – VAT payable (if any)
- Transfer the difference between the trial production costs and the proceeds from selling the trial output:
- Where the trial production costs exceed the proceeds from selling the trial output, the enterprise transfers the difference to increase capital construction investment costs in progress, recording:
Dr Account 241 – Construction in progress
Cr Account 154 – Work in progress.
- Where the trial production costs are less than the proceeds from selling the trial output, the enterprise transfers the difference to reduce capital construction investment costs in progress, recording:
Dr Account 154 – Work in progress
Cr Account 241 – Construction in progress.
c) When the trial running is completed and the fixed asset is handed over and brought to the condition necessary for it to be capable of operating in the manner intended by the enterprise, record:
Dr Account 211 – Tangible fixed assets
Cr Account 241 – Construction in progress.
3.2. Accounting for capital construction investment costs
3.2.1. Where advances are paid to contractors for capital construction, periodic repair and maintenance or upgrading and renovation of fixed assets, based on the relevant documents:
- Recognise the amount advanced to the contractor under the contract, recording:
Dr Account 331 – Payables to suppliers
Dr Account 133 – Deductible VAT (if any)
Cr Accounts 111, 112, etc.
- When receiving completed volumes of capital construction, periodic repair and maintenance or upgrading and renovation of fixed assets from the contractor, based on the relevant documents, record:
Dr Account 241 – Construction in progress (2412, 2413, 2414)
Dr Account 133 – Deductible VAT (if any)
Cr Account 331 – Payables to suppliers.
3.2.2. When receiving completed volumes of capital construction, periodic repair and maintenance or upgrading and renovation of fixed assets handed over by the contractor, or when construction investment costs are incurred under the self-performed method, based on the relevant documents, record:
Dr Account 241 – Construction in progress (2412, 2413, 2414)
Dr Account 133 – Deductible VAT (1332) (if any)
Cr Accounts 111, 112, 331, 335, etc.
3.2.3. When purchasing equipment for capital construction investment, based on the invoice and goods received note, record:
Dr Account 152 – Raw materials and supplies
Dr Account 133 – Deductible VAT (1332) (if any)
Cr Account 331 – Payables to suppliers (total payment amount).
Where equipment not requiring installation is delivered directly to the construction site and handed over to the contractor, record:
Dr Account 241 – Construction in progress
Dr Account 133 – Deductible VAT (1332) (if any)
Cr Account 331 – Payables to suppliers
Cr Account 151 – Goods in transit.
3.2.4. Payments to contractors and suppliers of materials, goods and services related to capital construction investment, record:
Dr Account 331 – Payables to suppliers
Cr Accounts 111, 112, etc.
3.2.5. Issue of capital construction investment equipment to the contractor:
a) For equipment not requiring installation, record:
Dr Account 241 – Construction in progress
Cr Account 152 – Raw materials and supplies.
b) For equipment requiring installation:
- When equipment is issued to the contractor, the enterprise only monitors in detail the equipment sent for installation.
- Only when the contractor hands over the completed installation volume, and it is accepted and approved for payment, is the value of the equipment sent for installation included in capital construction investment costs, recording:
Dr Account 241 – Construction in progress (2412)
Cr Account 152 – Raw materials and supplies.
3.2.6. When borrowing costs (including loan interest and costs of obtaining the loan) are incurred and are eligible for capitalisation as prescribed, bidding costs (after offsetting against proceeds from selling bidding documents), and costs of dismantling and restoring the site (after offsetting against recoverable scrap), etc., record:
Dr Account 241 – Construction in progress (2412)
Dr Account 133 – Deductible VAT (1332) (if any)
Cr Accounts 111, 112, 331, 335, 3411, 343, etc.
Proceeds from selling bidding documents, after offsetting against bidding costs, if there is a surplus, are recorded as a reduction of construction investment costs (credited to Account 241).
3.2.7. Penalties collected from contractors which, in substance, reduce the amount payable to the contractor, record:
Dr Accounts 112, 331
Cr Account 241 – Construction in progress.
3.2.8. When a work or work item is completed, its acceptance has been carried out, the asset has been handed over and the fixed asset has been brought to the condition necessary for it to be capable of operating in the manner intended by the enterprise:
- If the final settlement is approved immediately, the entry is based on the approved value of the asset created through the investment.
- If the final settlement has not yet been approved, the increase in the value of the asset created through the investment is recorded at a provisional value (the provisional value is the actual cost incurred to obtain the asset, determined based on Account 241).
In both cases, record as follows:
Dr Accounts 211, 213, 217
Cr Account 241 – Construction in progress (approved value or provisional value).
- Where capital construction expenditures are not approved by the competent authority and must be recovered, record:
Dr Account 138 – Other receivables
Cr Account 241 – Construction in progress
- Where a work has been completed but not yet accepted and the procedures for handing over the asset for use have not yet been carried out, pending preparation or approval of the final settlement, the enterprise must open a detailed ledger for Account 241 – Construction in progress to separately monitor completed works awaiting handover and approval of the final settlement.
3.2.9. When the final settlement of completed capital construction investment is approved, the enterprise adjusts the provisional value to the approved value of the asset, recording:
- If the approved value of the asset created through capital construction investment is lower than the provisional value:
Dr Account 138 – Other receivables (if the competent authority decides that the costs not approved and written off must be recovered)
Cr Accounts 211, 213, 217, etc.
- Where the approved value of the asset created through capital construction investment is higher than the provisional value or higher than the capital construction investment costs (if any, as prescribed by law), based on the decision of the competent authority on the treatment of the excess, record:
Dr Accounts 211, 213, 217, 155, etc.
Cr Related accounts.
- If the fixed asset is created using the welfare fund and is used for welfare purposes, when the investor approves the final settlement of the investment capital, the enterprise records an increase in the welfare fund used to acquire fixed assets:
Dr Account 3532 – Welfare fund
Cr Account 3533 – Welfare fund used to acquire fixed assets.
3.2.10. Where an investment project is cancelled or revoked, the enterprise liquidates the project and recovers the investment costs. The difference between the investment costs and the proceeds from the liquidation is recognised in other expenses or as compensation from responsible organisations or individuals under the handling decision of the competent authority, recording:
Dr Accounts 111, 112 (proceeds from the liquidation of the project)
Dr Account 138 – Other receivables (amount to be compensated by organisations or individuals)
Dr Account 811 – Other expenses (amount charged to other expenses)
Cr Account 241 – Construction in progress.
3.2.11. Where the enterprise, as the investor, establishes dependent units in the form of project management boards to perform the accounting for capital construction investment activities:
a) Accounting at the investor:
- Where a work whose final settlement has been approved is handed over, the investor recognises the value of the work at the approved settlement value, recording:
Dr Accounts 211, 213, 217, etc.
Dr Account 133 – Deductible VAT (if any)
Dr Accounts 111, 112, 152, 153
Cr Account 136 – Intra-company receivables
Cr Accounts 331, 333, etc. (liabilities assumed, if any).
- Where a work whose final settlement has not yet been approved is handed over, the investor recognises the value of the work at the provisional value. Upon final settlement, the value of the work must be adjusted to the approved settlement value, recording:
- If the approved settlement value is higher than the provisional value, record:
Dr Accounts 211, 213, 217, etc.
Cr Related accounts.
- If the approved settlement value is lower than the provisional value, record:
Dr Related accounts
Cr Accounts 211, 213, 217, etc.
b) Accounting at the project management board: Depending on the characteristics of its production and business activities and its management requirements, the enterprise provides accounting guidance to the project management boards under it, consistent with the principles set out in Article 7 of this Circular, the law on construction investment and other relevant laws.
3.3. Accounting for periodic repair and maintenance of fixed assets
Repairs of the enterprise’s fixed assets may also be carried out by the enterprise itself or by contractors.
a) When periodic repair and maintenance costs of fixed assets are incurred, they are accumulated on the debit side of Account 241 – Construction in progress (2413) and broken down by each fixed asset repair work or job. The entries are based on the documents relating to the costs incurred:
- If input VAT is deductible, record:
Dr Account 241 – Construction in progress (2413) (purchase price exclusive of VAT)
Dr Account 133 – Deductible VAT (1332)
Cr Accounts 111, 112, 152, 214, etc. (total payment amount).
- If input VAT is not deductible, the repair costs of fixed assets include VAT, recording:
Dr Account 241 – Construction in progress (2413) (total payment amount)
Cr Accounts 111, 112, 152, 214, 334, etc. (total payment amount).
b) When the periodic repair and maintenance work or work item is completed, handed over and put into use:
- Transfer the periodic repair and maintenance costs to deferred costs, recording:
Dr Account 242 – Deferred costs (periodic repair and maintenance costs to be allocated gradually)
Cr Account 241 – Construction in progress (2413).
- Allocate gradually to production and business costs of the department using the asset:
Dr Accounts 623, 627, 641, 642, etc.
Cr Account 242 – Deferred costs
3.4. Accounting for upgrading and renovation of fixed assets
- Accumulate the costs of upgrading and renovating fixed assets, recording:
Dr Account 241 – Construction in progress (2414)
Cr Accounts 112, 331, etc.
- Transfer to increase the historical cost of fixed assets when the renovation and upgrading of fixed assets is completed and handed over for use:
- Where the final settlement of the work is approved immediately upon handover, record:
Dr Account 211 – Tangible fixed assets
Cr Account 241 – Construction in progress (2414).
- Where a work whose final settlement has not yet been approved is handed over, the investor recognises the value of the work at the provisional value; the accounting is similar to that for the capital construction of new fixed assets.
Source: full text of Circular 99/2025/TT-BTC published in the Official Gazette. Download the PDF here. The content has been reformatted for easier reference; please refer to the original text when applying it.