Account 337 – Progress billings under construction contracts

TK 337Circular 99/2025Updated 26/11/2026

Extract from Appendix II – Circular 99/2025/TT-BTC dated 27 October 2025 of the Ministry of Finance, applicable to financial years beginning on or after 1 January 2026.

Category: Liability accounts

See also: Accounting principles for liabilities

1. Accounting principles

a) This account is used to reflect the amounts payable by customers according to the planned progress schedule and the amounts receivable based on the revenue corresponding to the portion of work completed, as determined by the contractor itself, under construction contracts in progress.

b) This account applies only where the construction contract provides that the contractor is paid according to the planned progress schedule; it does not apply where the construction contract provides that the contractor is paid according to the value of work performed as confirmed by the customer.

c) The basis for recording on the Debit side of Account 337 is the document determining the revenue corresponding to the portion of work completed in the period (not an invoice), prepared by the contractor itself without waiting for the customer’s confirmation. The contractor must select a method for determining the portion of work completed and assign responsibility to the relevant departments for determining the value of the work completed and preparing the documents reflecting construction contract revenue for the period.

The basis for recording on the Credit side of Account 337 is the invoice issued on the basis of the planned payment schedule stipulated in the contract. The amount stated on the invoice is the basis for recognising the amount receivable by the contractor from the customer; it is not the basis for recognising revenue in the accounting period.

d) Account 337 must be tracked in detail for each construction contract.

2. Structure and content of Account 337 – Progress billings under construction contracts

Debit side:

Reflects the amounts receivable based on the revenue recognised corresponding to the portion of work completed under construction contracts in progress.

Credit side:

Reflects the amounts payable by customers according to the planned progress schedule of construction contracts in progress.

Debit balance:

Reflects the difference where the revenue recognised under the contract exceeds the amounts payable by the customer according to the planned progress schedule of construction contracts in progress.

Credit balance:

Reflects the difference where the revenue recognised under the contract is less than the amounts payable by the customer according to the planned progress schedule of construction contracts in progress.

3. Accounting method for certain principal economic transactions

a) Where the construction contract provides that the contractor is paid according to progress, when the outcome of the construction contract can be estimated reliably, the accountant shall, on the basis of the documents reflecting the revenue corresponding to the portion of work completed (not invoices) as determined by the contractor itself, record:

Dr Account 337 – Progress billings under construction contracts
Cr Account 511 – Revenue from sales of goods and rendering of services.

b) On the basis of invoices issued according to progress, to reflect the amounts receivable according to the progress stated in the contract, record:

Dr Account 131 – Receivables from customers
Cr Account 337 – Progress billings under construction contracts
Cr Account 3331 – VAT payable.

c) When the contractor receives payment from the customer, record:

Dr Accounts 111, 112
Cr Account 131 – Receivables from customers.


Source: full text of Circular 99/2025/TT-BTC published in the Official Gazette. Download the PDF here. The content has been reformatted for easier reference; please refer to the original text when applying it.