1. Accounting principles
a) This account is used to accumulate production and business costs for calculating the cost of products and services at enterprises applying the perpetual inventory method in accounting for inventories. At enterprises applying the periodic inventory method, Account 154 reflects only the actual value of products and services in progress at the end of the period.
b) Account 154 “Work in progress” reflects production and business costs incurred during the period; production and business costs of products and services completed during the period; and opening and closing work in progress of main and ancillary production and business activities and outsourced processing at manufacturing enterprises or service enterprises. Account 154 also reflects production and business costs of manufacturing, processing or service activities of trading enterprises, if they carry out such activities.
c) Production and business costs recorded in Account 154 must be detailed by the place where the costs are incurred (workshop, production department, production team, construction site, etc.); by type or group of products, or by product component or part; by type of service or by service stage.
d) Production and business costs reflected in Account 154 comprise the following:
– Direct raw material costs;
– Direct labour costs;
– Construction machinery costs (for construction and installation activities);
– Production overheads.
đ) Raw material and labour costs in excess of normal levels and unallocated fixed production overheads are not included in the value of inventories but must be charged to cost of goods sold for the accounting period.
e) At the end of the period, fixed production overheads are allocated and transferred to the conversion cost of each unit of product based on normal capacity (Cr Account 627, Dr Account 154). Where the actual level of production is lower than normal capacity, the accountant must calculate and determine the fixed production overheads allocated to the conversion cost of each unit of product based on normal capacity. Unallocated fixed production overheads (not included in product cost) are recognised in cost of goods sold for the period (Cr Account 627, Dr Account 632). Variable production overheads are fully allocated to the conversion cost of each unit of product based on actual costs incurred.
g) The following costs are not recorded in Account 154:
– Selling expenses;
– General and administrative expenses;
– Financial expenses;
– Other expenses;
– Corporate income tax expense;
– Non-business and project expenditure;
– Capital construction investment expenditure;
– Expenditure covered by other sources.
2. Application of Account 154 in the industrial sector
a) Account 154 “Work in progress” as applied in the industrial sector is used to accumulate and aggregate production costs and calculate the product cost of workshops or production and manufacturing departments. For manufacturing enterprises that outsource processing, or provide labour services and services to outside parties or to support product manufacturing, the costs of these activities are also accumulated in Account 154.
b) Only the following cost items may be reflected in Account 154:
– Direct raw material costs for manufacturing products;
– Direct labour costs for manufacturing products;
– Production overheads directly serving the manufacture of products.
c) Account 154 at industrial manufacturing enterprises is recorded in detail by the place where costs are incurred (workshop, production department), by type or group of products, by product, or by product component.
d) For industrial manufacturing enterprises that outsource processing, or provide labour services and services to outside parties or to support product manufacturing, the costs of these activities are also accumulated in Account 154.
3. Application of Account 154 in the agricultural sector
a) Account 154 “Work in progress” as applied in the agricultural sector is used to accumulate total production costs and calculate the product cost of cultivation and husbandry, product processing or agricultural services. This account must be recorded in detail by agricultural business line (crop cultivation, animal husbandry, processing, etc.), by the place where costs are incurred (workshop, production team, etc.), and by each type of crop or livestock and each type of product, each product or service.
b) The actual production cost of agricultural products is determined at the end of the harvest season or at year end. Products harvested in a given year are costed in that year; that is, costs incurred this year for products harvested only next year are costed next year.
c) For crop cultivation, costs must be recorded in detail for 3 types of crops:
– Short-term crops (rice, sweet potatoes, cassava, etc.);
– Crops planted once and harvested many times (pineapples, bananas, etc.);
– Perennial crops (tea, coffee, rubber, pepper, fruit trees, etc.).
For crops grown in 2 or 3 seasons a year, or planted this year and harvested next year, or crops with both newly planted areas and areas under care and harvest in the same year, etc., records must be based on the actual situation, clearly reflecting the costs of each season, each area, and of the previous, current and following years, etc.
d) This account does not reflect costs of land reclamation, new planting and care of perennial crops during the capital construction period, selling expenses, general and administrative expenses, financial expenses or other expenses.
đ) In principle, crop cultivation production costs are recorded in detail on the Debit side of Account 154 “Work in progress” for each cost object. Certain costs relating to several cost objects, or to several seasons or periods, must be reflected in separate accounts and then allocated to the cost of the related products, such as: irrigation and drainage costs, land preparation and first-year planting costs of crops planted once and harvested many times (these costs are not capital construction investment), etc.
e) On the same cultivated area, if two or more short-term crops are intercropped, costs directly related to a particular crop are accumulated separately for that crop (such as seeds, sowing and harvesting costs, etc.); common costs for several crops (ploughing, irrigation and drainage costs, etc.) are accumulated separately and allocated to each crop based on the planted area or other appropriate criteria.
g) For perennial crops, the process from land preparation, sowing and care until the crops start producing (first harvest) is accounted for as a capital construction investment process forming fixed assets, with costs accumulated in Account 241 “Construction in progress”. Costs for perennial plantations during production and business include costs of care and harvesting.
h) When recording animal husbandry costs in Account 154, the following points should be noted:
– Animal husbandry costs must be recorded in detail for each type of husbandry activity (such as cattle and buffalo raising, pig raising, etc.), and by group or type of livestock and poultry;
– Young animals born to the breeding herd or fattening herd, after weaning, are tracked in a separate detailed ledger at actual cost;
– Breeding animals culled and transferred to rearing or fattening are recorded in Account 154 at the net book value of the breeding animals;
– Costing units in animal husbandry are: 1 kg of fresh milk, 1 standard calf, cost of 1 kg of weight gain, cost of 1 kg of live weight, cost of 1 animal-day of husbandry, etc.
i) Raw material and direct labour costs in excess of normal levels and unallocated fixed production overheads are not included in product cost but are charged to cost of goods sold for the accounting period.
4. Application of Account 154 in the service sector
a) Account 154 “Work in progress” applies to service enterprises such as: transport, postal services, tourism, services, etc. This account is used to accumulate total costs (direct raw materials, direct labour, production overheads) and calculate the cost of services performed.
b) For the transport sector, this account is used to accumulate costs and calculate the cost of road transport (cars, trams, transport by other rudimentary means, etc.), rail transport, waterway transport, air transport, pipeline transport, etc. Account 154 as applied in the transport sector must be detailed for each type of activity (passenger transport, freight transport, etc.) by each enterprise or service business unit.
c) In the course of transport, tyres and inner tubes wear out faster than the depreciation rate of the vehicle and therefore usually have to be replaced many times; however, the value of replacement tyres is not charged to transport cost all at once when issued for replacement but must be allocated month by month. Therefore, road transport enterprises may accrue tyre costs monthly in the transport cost (accrued expenses) in accordance with the current financial regime.
d) Raw material and direct labour costs in excess of normal levels and unallocated fixed production overheads are not included in product cost but are charged to cost of goods sold for the accounting period.
đ) For tourism business activities, this account is detailed by type of activity, such as: tour guiding, hotel business, tourist transport business, etc.
e) In hotel business activities, Account 154 must be detailed by type of service, such as: food and beverage, accommodation, recreation and entertainment, and other services (laundry, ironing, hairdressing, telegraph, sports, etc.).
5. Application of Account 154 in the construction sector
a) Construction and installation business activities are required to apply only the perpetual inventory method and not the periodic inventory method; therefore, Account 154 is used to accumulate production and business costs for calculating the production cost of industrial construction and installation products and services of construction and installation enterprises.
b) Direct raw material and direct labour costs in excess of normal levels and unallocated fixed production overheads are not included in the cost of construction and installation works but are charged to cost of goods sold for the accounting period.
c) In the Construction and installation sector, this account has 4 level-2 accounts:
– Account 1541 – Construction and installation: Used to accumulate costs, calculate the production cost of construction and installation products and reflect the value of construction and installation products in progress at the end of the period;
– Account 1542 – Other products: Used to accumulate costs, calculate the production cost of other products and reflect the value of other products in progress at the end of the period (finished goods, construction components, etc.);
– Account 1543 – Services: Used to accumulate costs, calculate the cost of services and reflect service costs in progress at the end of the period;
– Account 1544 – Construction and installation warranty costs: Used to accumulate the costs of warranty for construction and installation works actually incurred during the period and the value of construction and installation warranty works in progress at the end of the period.
d) Production costs must be accumulated and the cost of construction and installation products calculated for each work and work item and by the cost items specified in the construction and installation estimate, comprising:
– Material costs;
– Labour costs;
– Construction machinery costs;
– Overhead costs.
Overhead costs accumulated on the Debit side of Account 1541 “Construction and installation” include only overheads incurred at the contracting team or construction site. General and administrative expenses of the construction and installation enterprise (which are part of overhead costs) are accumulated on the Debit side of Account 642 “General and administrative expenses”. These expenses are transferred to the Debit side of Account 911 “Determination of business results” and form part of the full cost of construction and installation products completed and sold during the period.
đ) Real estate developers use this account to accumulate the construction costs of real estate finished goods. Where the real estate constructed is used for multiple purposes (as offices, for lease or for sale, e.g. a mixed-use apartment building), the following principles apply:
– If there are sufficient grounds to account separately for, or to determine the proportion of, the construction costs of real estate for sale (real estate finished goods) and the construction costs of real estate for lease or for use as offices (fixed assets or investment property), the construction costs of real estate finished goods must be recorded separately in Account 154. The construction costs of fixed assets or investment property are reflected separately in Account 241 – Construction in progress.
– Where it is not possible to account separately for, or to determine the proportion of, construction costs attributable to the components of real estate finished goods, fixed assets or investment property, the accountant accumulates the costs directly related to the construction investment in Account 241. When the work or project is completed, handed over and put into use, the accountant transfers the construction investment costs in accordance with the nature of each type of asset, based on how the asset is actually used.
**6. Structure and content of Account 154 – Work in progress
Debit side:**
– Direct raw material costs, direct labour costs, construction machinery costs and production overheads incurred during the period relating to the manufacture of products and the performance of services;
– Direct raw material costs, direct labour costs, construction machinery costs and production overheads incurred during the period relating to the cost of construction and installation works or the construction and installation cost under internal fixed-price contracts;
– Transfer of closing work in progress (where the enterprise accounts for inventories under the periodic inventory method).
Credit side:
– Actual production cost of products manufactured and received into the warehouse, sent for sale, consumed internally immediately or used immediately in capital construction;
– Production cost of construction and installation products completed and handed over in part or in full and sold during the period; or handed over to the main construction contractor (superior or internal); or the cost of completed construction and installation products awaiting sale;
– Actual cost of services completed and provided to customers;
– Value of recovered scrap and value of irreparable defective products;
– Value of raw materials and goods returned to the warehouse after processing;
– Reflects raw material and labour costs in excess of normal levels and unallocated fixed production overheads, which are not included in the value of inventories but must be charged to cost of goods sold for the accounting period. For enterprises producing to order, or enterprises with a long production cycle that transfer fixed production overheads to Account 154 each accounting period, the fixed production overheads not included in the value of inventories can only be determined when the products are completed, and must be charged to cost of goods sold (Cr Account 154, Dr Account 632);
– Transfer of opening work in progress (where the enterprise accounts for inventories under the periodic inventory method).
Debit balance:
Production and business costs still in progress at the end of the period.
7. Accounting method for certain major economic transactions in the Industrial sector
7.1. Where inventories are accounted for under the perpetual inventory method
a) At the end of the period, the accountant transfers direct raw material costs by each cost object, record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (raw material costs in excess of normal levels) Cr Account 621 – Direct raw material costs.
b) At the end of the period, the accountant transfers direct labour costs by each cost object, record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (labour costs in excess of normal levels) Cr Account 622 – Direct labour costs.
c) Where the actual level of production is higher than or equal to normal capacity, at the end of the period the accountant calculates, allocates and transfers all production overheads (variable and fixed production overheads) to each cost object, record:
Dr Account 154 – Work in progress Cr Account 627 – Production overheads.
d) Where the actual level of production is lower than normal capacity, the accountant must calculate and determine the fixed production overheads allocated to the conversion cost of each unit of product based on normal capacity. Unallocated fixed production overheads (not included in product cost, being the excess of total fixed production overheads actually incurred over the fixed production overheads included in product cost) are recognised in cost of goods sold for the period, record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (fixed production overheads not allocated to product cost) Cr Account 627 – Production overheads.
đ) Value of raw materials sent out for processing and returned to the warehouse, record:
Dr Account 152 – Raw materials
Cr Account 154 – Work in progress.
e) Value of irreparable defective products for which the person causing the damage must pay compensation, record:
Dr Account 138 – Other receivables (1388) Dr Account 334 – Payables to employees Cr Account 154 – Work in progress.
g) For enterprises with a long production and business cycle that have transferred direct raw material costs, direct labour costs and production overheads to Account 154 during the accounting period, when raw material and direct labour costs in excess of normal levels and fixed production overheads not included in product cost are determined, the accountant reflects the raw material and labour costs in excess of normal levels and unallocated fixed production overheads (not included in the value of inventories), which must be charged to cost of goods sold for the accounting period, record:
Dr Account 632 – Cost of goods sold Cr Account 154 – Work in progress (where costs have been transferred from Accounts 621, 622, 627 to Account 154).
h) Actual cost of products received into the warehouse during the period, record:
Dr Account 155 – Finished goods Cr Account 154 – Work in progress.
i) Where products manufactured are consumed internally immediately or issued directly for capital construction without passing through the warehouse, record:
Dr Accounts 641, 642, 241 Cr Account 154 – Work in progress.
k) Where, after raw materials have been issued for production, trade discounts or sales allowances (including contractual penalties that in substance reduce the amount payable by the buyer) relating to those raw materials are received, the accountant reduces work in progress costs by the trade discounts and allowances received corresponding to the raw materials issued for producing work in progress:
Dr Accounts 111, 112, 331,…. Cr Account 154 – Work in progress (trade discounts and sales allowances received corresponding to the raw materials issued for producing work in progress) Cr Account 133 – Deductible VAT (1331) (if any).
l) Accounting for trial products:
– Trial production costs are accumulated in Account 154 as for other products. When trial products are recovered (sold or liquidated), record:
Dr Accounts 111, 112, 131 Cr Account 154 – Work in progress Cr Account 3331 – VAT payable (if any).
– Transfer of the difference between trial production costs and proceeds from the sale or liquidation of trial products:
+ If trial production costs exceed the proceeds from the sale or liquidation of trial products, the accountant increases the value of the construction investment asset, record:
Dr Account 241 – Construction in progress Cr Account 154 – Work in progress.
+ If trial production costs are less than the proceeds from the sale or liquidation of trial products, the accountant reduces the value of the construction investment asset, record:
Dr Account 154 – Work in progress Cr Account 241 – Construction in progress.
m) Where completed products are not received into the warehouse but delivered directly to the buyer (electricity, water, etc.), record:
Dr Account 632 – Cost of goods sold Cr Account 154 – Work in progress.
7.2. Where inventories are accounted for under the periodic inventory method:
a) At the end of the accounting period, based on the actual stocktaking results, determine the actual value of work in progress and make the transfer, record:
Dr Account 154 – Work in progress Cr Account 631 – Production cost.
b) At the beginning of the accounting period, transfer the actual cost of work in progress, record:
Dr Account 631 – Production cost Cr Account 154 – Work in progress.
8. Accounting method for certain major economic transactions in the Agricultural sector
8.1. Where inventories are accounted for under the perpetual inventory method
a) At the end of the period, the accountant calculates and transfers direct raw material costs by cost object, record:
Dr Account 154 – Work in progress
Dr Account 632 – Cost of goods sold (raw material costs in excess of normal levels) Cr Account 621 – Direct raw material costs.
b) At the end of the period, the accountant calculates and transfers direct labour costs by each cost object, record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (labour costs in excess of normal levels) Cr Account 622 – Direct labour costs.
c) At the end of the period, the accountant calculates, allocates and transfers production overheads to each cost object, record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (fixed production overheads not allocated to product cost) Cr Account 627 – Production overheads.
d) Value of by-products recovered, record:
Dr Account 152 – Raw materials Cr Account 154 – Work in progress.
đ) Value of recovered scrap and raw materials sent out for processing and returned to the warehouse, record:
Dr Account 152 – Raw materials Cr Account 154 – Work in progress.
e) Value of young animals and fattening animals transferred to working animals or breeding animals, record:
Dr Account 211 – Tangible fixed assets (2116) Cr Account 154 – Work in progress.
g) Actual production cost of products completed and received into the warehouse or sold immediately, record:
Dr Account 155 – Finished goods Dr Account 632 – Cost of goods sold Cr Account 154 – Work in progress.
h) Where products manufactured are consumed internally immediately without passing through the warehouse, record:
Dr Accounts 641, 642, 241 Cr Account 154 – Work in progress.
8.2. Where inventories are accounted for under the periodic inventory method:
The recording method for certain major economic transactions in Account 154 in the Agricultural sector is similar to that for the Industrial sector.
9. Accounting method for certain major economic transactions in the service business sector
The accounting method for certain major economic transactions in Account 154 at enterprises in the service business sector is similar to that for the industrial sector. In addition, note the following:
a) Transfer of the actual cost of services completed, delivered to the buyer and determined to have been sold during the period, record:
Dr Account 632 – Cost of goods sold
Cr Account 154 – Work in progress.
b) When services are consumed internally, record:
Dr Accounts 641, 642 Cr Account 154 – Work in progress.
10. Accounting method for certain major economic transactions in the construction sector
10.1. Method of recording the accumulation of construction and installation costs (Debit side of Account 1541 “Construction and installation”):
a) Recording direct raw material costs:
– Direct raw material costs comprise: the actual value of main materials, auxiliary materials, components or separate parts, and reusable materials forming part of the construction and installation product or helping to perform and complete the construction and installation work (excluding auxiliary materials for construction machinery and equipment and materials included in overhead costs).
– Principles for recording direct raw material costs: raw materials used for the construction of a particular work item must be charged directly to that work item on the basis of source documents, according to the actual quantity used and the actual cost of issue (weighted average; first-in, first-out; specific identification).
– At the end of the accounting period or when the work is completed, a stocktake of the materials remaining at the production site (if any) is carried out to reduce the direct raw material costs issued for the work.
– Where actual construction and installation conditions do not permit direct raw material costs to be charged to each work or work item, the enterprise may allocate materials to the users on a reasonable basis (in proportion to raw material consumption norms, etc.).
– Based on the Material allocation schedule for each work and work item, record:
Dr Account 154 – Work in progress (material costs) Dr Account 632 – Cost of goods sold (direct raw material costs in excess of normal levels) Cr Account 621 – Direct raw material costs.
b) Recording direct labour costs: recorded in the same way as for the industrial sector
c) Recording construction machinery costs:
– Construction machinery costs comprise: costs of construction machinery used to perform construction and installation work by machine. Construction machinery is machinery that directly serves the construction and installation of works. It includes machinery powered by steam, diesel, petrol or electric motors, etc. (including machinery serving construction and installation).
– Construction machinery costs comprise recurrent costs and temporary costs. Recurrent costs for the operation of construction machinery comprise: labour costs of machine operators and attendants, etc.; material costs; tools and supplies costs; depreciation of fixed assets; outsourced service costs (minor repairs, electricity, water, vehicle and machinery insurance, etc.); and other cash expenses.
– Temporary costs for the operation of construction machinery comprise: costs of major repairs of construction machinery (major overhauls, intermediate overhauls, etc.) not qualifying for an increase in the historical cost of the machinery; costs of temporary works for construction machinery (sheds, shelters, platforms, machine rails, etc.). Temporary machinery costs may be incurred in advance (recorded on the Debit side of Account 242) and then gradually allocated to the Debit side of Account 623 “Construction machinery costs”; or incurred later but accrued in advance to construction and installation production costs for the period (because they relate to the actual use of construction machinery during the period). In this case, costs must be accrued in advance by crediting Account 352 “Provisions for payables” and debiting Account 623 “Construction machinery costs”.
– The accumulation of costs and calculation of construction machinery costs must be recorded separately for each machine (see the guidance on Account 623 “Construction machinery costs”).
– Based on the Construction machinery cost allocation schedule (actual machine-shift costs) for each work and work item, record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (costs in excess of normal levels) Cr Account 623 – Construction machinery costs.
d) Recording production overheads:
– Production overheads reflect the production costs of construction teams and sites, comprising: salaries of management staff of workshops, groups and construction teams; social insurance, health insurance and trade union fee contributions calculated at the prescribed rates on the salaries payable to direct construction workers, construction machinery operators and management staff of workshops, groups and teams; depreciation of fixed assets used in common for team activities and other costs relating to team activities, etc. When these costs are incurred during the period, record:
Dr Account 627 – Production overheads Dr Account 133 – Deductible VAT (if any) Cr Accounts 111, 112, 152, 153, 214, 242, 334, 338,…
– When determining the provision for warranty of construction and installation works, record:
Dr Account 627 – Production overheads Cr Account 352 – Provisions for payables.
– When costs of repair and warranty of works are incurred, such as direct raw material costs, direct labour costs, construction machinery costs and production overheads, the accountant records them in the relevant cost accounts, record:
Dr Account 621 – Direct raw material costs Dr Account 622 – Direct labour costs Dr Account 623 – Construction machinery costs Dr Account 627 – Production overheads Dr Account 133 – Deductible VAT (if any) Cr Accounts 112, 152, 153, 214, 331, 334, 338,…
– At the end of the period, transfer the actual direct raw material, direct labour, construction machinery and production overhead costs incurred during the period relating to the repair and warranty of construction and installation works, in order to aggregate repair and warranty costs and calculate the warranty cost, record:
Dr Account 154 – Work in progress Cr Account 621 – Direct raw material costs Cr Account 622 – Direct labour costs Cr Account 623 – Construction machinery costs Cr Account 627 – Production overheads.
– When the warranty repair work on construction and installation works is completed and handed over to the customer, record:
Dr Account 352 – Provisions for payables Cr Account 154 – Work in progress.
– At the end of the warranty period for construction and installation works, if no warranty work is required or the provision for warranty of construction and installation works exceeds the actual costs incurred, the difference must be reversed, record:
Dr Account 352 – Provisions for payables Cr Account 711 – Other income.
– At the end of the accounting period, based on the Production overhead allocation schedule, allocate and transfer production overheads to the relevant works and work items (in proportion to labour costs), record:
Dr Account 154 – Work in progress Dr Account 632 – Cost of goods sold (unallocated fixed production overheads not included in the cost of construction and installation works) Cr Account 627 – Production overheads.
10.2. Method of recording and transferring construction and installation costs (Credit side of Account 1541 “Construction and installation”):
a) Contract costs that cannot be recovered (e.g. contracts that are not fully enforceable legally, such as where their validity is in doubt, or contracts where the customer cannot fulfil its obligations, etc.) must be recognised immediately as an expense in the period, record:
Dr Account 632 – Cost of goods sold Cr Account 154 – Work in progress.
b) Costs directly attributable to each contract may be reduced by other income not included in contract revenue. For example: proceeds from the sale of surplus raw materials and the liquidation of construction machinery and equipment at the end of the construction contract:
– Surplus raw materials received into the warehouse at the end of the construction contract, record:
Dr Account 152 – Raw materials (at cost) Cr Account 154 – Work in progress.
– Recovered scrap received into the warehouse, record:
Dr Account 152 – Raw materials (at recoverable value) Cr Account 154 – Work in progress.
– Where surplus materials and recovered scrap are sold immediately without passing through the warehouse, the accountant reflects the proceeds from the sale of surplus materials and scrap as a reduction of costs:
Dr Accounts 111, 112, 131,… (total payment amount) Cr Account 3331 – VAT payable (33311) Cr Account 154 – Work in progress.
– Accounting for the liquidation of construction machinery and equipment used exclusively for a construction contract, where the fixed assets have been fully depreciated by the end of the construction contract:
+ Reflect the proceeds from the liquidation of construction machinery and equipment, record:
Dr Accounts 111, 112, 131,… Cr Account 3331 – VAT payable (33311) Cr Account 154 – Work in progress.
+ Reflect the costs of liquidating machinery and equipment (if any), record:
Dr Account 154 – Work in progress Dr Account 133 – Deductible VAT (1331) Cr Accounts 111, 112,…
+ Derecognise the fully depreciated specialised construction machinery and equipment that have been liquidated, record:
Dr Account 214 – Depreciation of fixed assets Cr Account 211 – Tangible fixed assets.
c) At the end of the accounting period, based on the actual production cost of completed construction and installation products determined to have been sold (handed over in part or in full to the Project Management Board – party A), or handed over to the internal main contractor:
– Where handed over to Party A (including handover of construction and installation work completed under internal fixed-price contracts to a contracted unit with its own accounting organisation), record:
Dr Account 632 – Cost of goods sold Cr Account 154 – Work in progress (1541).
– Where completed construction and installation products are awaiting sale (houses built for sale, etc.) or completed but not yet handed over, based on the cost of the completed construction and installation products awaiting sale, record:
Dr Account 155 – Finished goods Cr Account 154 – Work in progress (1541).
– Where completed construction and installation products are handed over to the main construction and installation contractor (a superior or internal unit – under an internal construction and installation fixed-price contract, where the contracted unit has its own accounting organisation but only accounts up to the construction and installation production cost), record:
Dr Account 336 – Intra-company payables (3368) Cr Account 154 – Work in progress (1541).