Account 337 – Progress billings under construction contracts
This content follows Circular 200/2014/TT-BTC, replaced by Circular 99/2025/TT-BTC from 1 January 2026. It is kept for reference to prior years.→ See Account 337 under Circular 99/2025/TT-BTC
1. Accounting principles
a) This account is used to reflect the amounts customers must pay according to the planned progress schedule and the amounts receivable corresponding to revenue for the portion of work completed, as determined by the contractor itself, under construction contracts in progress.
b) Account 337 “Progress billings under construction contracts” applies only where the construction contract stipulates that the contractor is paid according to the planned progress schedule. This account does not apply where the construction contract stipulates that the contractor is paid based on the value of work performed as certified by the customer.
c) The basis for recording on the Debit side of Account 337 is the document determining revenue corresponding to the portion of work completed during the period (not an invoice), prepared by the contractor itself without waiting for the customer’s certification. The contractor must select a method for determining the portion of work completed and assign responsibility to the relevant departments for determining the value of the work completed and preparing documents reflecting construction contract revenue for the period.
The basis for recording on the Credit side of Account 337 is the invoice issued on the basis of the planned payment schedule stipulated in the contract. The amount stated on the invoice is the basis for recognising the amount receivable by the contractor from the customer; it is not the basis for recognising revenue in the accounting period.
d) Account 337 must be tracked in detail for each construction contract.
**2. Structure and content of Account 337 – Progress billings under construction contracts
Debit side:** Reflects the amounts receivable corresponding to the revenue recognised for the portion of work completed under construction contracts in progress.
Credit side: Reflects the amounts customers must pay according to the planned progress schedule of construction contracts in progress.
Debit balance: Reflects the difference where recognised contract revenue exceeds the amounts customers must pay according to the planned progress schedule of construction contracts in progress.
Credit balance: Reflects the difference where recognised contract revenue is less than the amounts customers must pay according to the planned progress schedule of construction contracts in progress.
3. Accounting method for certain major economic transactions
a) Where the construction contract stipulates that the contractor is paid according to the planned progress schedule, and the outcome of the construction contract can be estimated reliably, the accountant, based on the documents reflecting revenue corresponding to the portion of work completed (not invoices) as determined by the contractor, records:
Dr Account 337 – Progress billings under construction contracts Cr Account 511 – Revenue from sales of goods and rendering of services.
b) Based on the invoices issued according to the planned progress schedule, to reflect the amounts receivable according to the planned schedule stated in the contract, record:
Dr Account 131 – Receivables from customers Cr Account 337 – Progress billings under construction contracts Cr Account 3331 – VAT payable.
c) When the contractor receives payment from the customer, record:
Dr Accounts 111, 112 Cr Account 131 – Receivables from customers.